Specialists from the Republic Enterprise Regional Energy Supply Company restored a stable power supply to the residents of Yasnoye (suburb of Dokuchayevsk). It was disrupted the day before as a result of attacks by the armed formations of Ukraine on the DPR territory.
According to a duty officer of the DPR Ministry of Coal and Energy, emergency repair crews surveyed the 6 kV power line and promptly remedied the damage caused by Kiev militants’ firing. At 9:50 a.m., the power supply to all subscribers and social facilities resumed.
Now the power supply of the village is carried out in a normal mode.
We remind you that on February 17 at 19:00 Kiev militants damaged the 6 kV power line, which supplies the village Yasnoye. 5 electrical substations were de-energized, 520 domestic subscribers, a kindergarten, a pumping house and a boiler house were left without electricity. That is, the villagers were left without both power and heating.
Unfortunately, it was not possible to carry out repair at night, as the power line goes in direct proximity to the delimitation line.